Skyline golf course at Marcella Jordanelle Ridge, Q1 '26

Marcella Jordanelle Ridge · Construction Update

Q1 '26

Published April 1, 2026

  1. Greens

    All green complexes are complete.

  2. Water feature

    The water feature on holes 1 and 18 is complete and filled.

  3. Creek

    A recirculating pump for the creek will be installed in April.

  4. Irrigation

    The irrigation system was de-winterized in March and is fully operational.

  5. Turf

    A light winter brought an early spring; the turf has managed through winter nicely and is greening up.