Aerial construction progress at Marcella Landing, Q1 '26

Marcella Landing · Construction Update

Q1 '26

Published April 1, 2026

  1. Clusters 1 & 2

    Mechanical, electrical, and plumbing trades are mobilized and installing. Cluster 1 is preparing for delivery of Leonardo window systems.

  2. Clusters 3 & 4

    Structural steel and framing have begun.

  3. Clusters 5 & 6

    Concrete walls and chimneys continue, preparing for steel deliveries.

  4. Cluster 7

    Footing and foundation work is underway.

  5. Ski amenity

    The drive retaining wall is complete and blasting is finished.

3 photographs·Q1 '26