Marcella Landing · Construction Update
Q1 '26
Published April 1, 2026
Clusters 1 & 2
Mechanical, electrical, and plumbing trades are mobilized and installing. Cluster 1 is preparing for delivery of Leonardo window systems.
Clusters 3 & 4
Structural steel and framing have begun.
Clusters 5 & 6
Concrete walls and chimneys continue, preparing for steel deliveries.
Cluster 7
Footing and foundation work is underway.
Ski amenity
The drive retaining wall is complete and blasting is finished.
3 photographs·Q1 '26