Construction Update
Q4 2025
Below are the construction updates on the progress being made at Marcella Landing at Deer Valley for August 2025.
- Building 1: Chimneys and wall completed through level 2.
- Building 2: Completed the first wall and chimney pours.
- Building 3: Concrete work to begin August 1.
- Building 4: Rebar in fabrication and preparing for late August installation.