Construction Update
Q1 '26
- Mechanical, electrical, and plumbing trades mobilized and installing in Cluster 1 and 2.
- Cluster 1 preparing for delivery of Leonardo Window systems
- Structural steel and framing have begun on Cluster 3 and 4
- Cluster 5 and 6 continuing concrete walls and chimneys preparing for steel deliveries.
- Footing and foundation work underway for Cluster 7
- Ski Amenity drive retaining wall and blasting complete.